Los Angeles Unified School District Northridge Middle School ADA Barrier Removal

 

 

Los Angeles Unified School District Northridge Middle School ADA Barrier Removal

Los Angeles, California

The project consisted of extensive alterations to an existing 1,150-student middle school campus situated on 30 acres with 35 buildings originally constructed in the 1950’s and 60’s.

Three separate general contractors were involved on the project (concrete fl atwork, general building alterations, & modular ramps) which required careful coordination and management of separate RFI’s, submittals, and change orders.

Adding to the complexity of the project was the fact that it was constructed simultaneously with a campus-wide pavement and site utililty replacement project with a separate contractor and AE team.

 
 
 

ADA Compliant Ramp

 

ADA Compliant Ramp

 
 
 

ADA Compliant Drinking Fountains

 
 
 

ADA Compliant Drinking Fountains

 
 
 

Site Plan

  • Accessible Route Upgrades and Barrier Removal

  • Accessible Parking Stalls

  • ADA Compliant Ramps

  • Accessible Gates, Doors, Thresholds, and/or Hardware

  • ADA Restroom Upgrades

  • Reception Counters Modification

  • ADA Compliant Classroom Sink

  • ADA Compliant Drinking Fountains

  • Gymnasium Locker Room Modification

  • ADA Compliant Signage

 

Education / Los Angeles Unified School District Northridge Middle School ADA Barrier Removal

 

Client

Los Angeles Unified School District

Team

KPFF, civil engineer & structural engineer
IMEG Corp., project executive electrical engineer